  • Delivery schedule adherence

    • 0
    • 4
    • 1
    • 0
    • 0
    • 0
    • 0
    • 0
    • 1.35k
    Comment on it

    It is the metrics used to calculate the number of delivery done in time against the planned delivery .Delivery schedule adherence is usually calculated by project manager or QA manager so that he can evaluate the performance of his team . The output of schedule adherence give the project manager a early warning , so that proper measure and process could be applied for enhancing the probability of project success. To calculate the Delivery Schedule adherence we use following formula :

    No of Delivery within schedule
    -------------------------------------- * 100
    No of Delivery Planned

    Example :
    Delivery planned = 7
    Actual Delivery =5

    5
    ---- * 100 = 71.43
    7

 0 Comment(s)

Sign In
                           OR                           
                           OR                           
Register

Sign up using

                           OR                           
Forgot Password
Fill out the form below and instructions to reset your password will be emailed to you:
Reset Password
Fill out the form below and reset your password: